2006
Plant Management Program on Peppermill Lake** |
The
current Peppermill Lake aquatic plant management effort was newly implemented
in 2005. We will follow the same plan in 2006, as specified in our Management
Plan, approved by the DNR last August. |
|
There are three parts to our plant management: |
With
this effort,we will contract for machine harvest as many as four different
times this coming summer: |
1.
Approximately Middle May - Harvest EWMF to a depth of 1 foot
of bottom (will depend on density of EWMF) 2. Late June (week before July 4th weekend) - Harvest lily pads and other plants, to facilitate navigation and to provide plant edges for fish habitate/increased panfish predation following approved map at Peppermill Website. 3..Mid August - Harvest lily pads and other plants, to facilitate navigation and to provide plant edges for fish habitate/increased panfish predation following approved map at Peppermill website. 4. Approximately Mid September – Harvest EWMF to a depth of one foot from bottom (will depend on density and presense of EWMF). |
In parallel, in May and September there will be spot chemical treatment
of EWMF in shallow areas where harvesting is not possible. We also will
be asking you to install small bags of barley straw bags at your pier
in early April. |
**Note:
Individual property owners may contract for harvesting, but that harvesting
cannot ocurr in shallow water (less than 3 feet), closer to shore than
the end of their piers, nor can it exceed certain boundaries. It also
requires a DNR permit. |